Norra Stålverket expansion
Approved cost to date€292.1k
frozen at approval
Pending exposure€491.4k
pending credits, not netted: −€120.0k
Contingency remaining€2.151m
of €2.500m
Approvals > 10 wd1
NSV-CR-0022 · 12 wd
Cycle time, raise → decision—
all decided to date
PM weekly · what is stuck
| Change | State | Actor | Days |
|---|---|---|---|
| NSV-CR-0021 | In Assessment | Sofia Ahlgren | 13 |
| NSV-CR-0022 | In Approval | Erik Sandström | 12 |
| NSV-CR-0019 | In Implementation | Jonas Berg | 8 |
Reminder at 5 working days in state; escalation notice at 10. Escalation notifies; it never auto-approves.
Where change comes from · category
Unforeseen site conditions €348.5k
Scope reduction / omission €120.0k
Design development / engineering change €82.9k
Schedule measure €82.4k
Contractor-driven variation €60.0k
Cumulative change by contract
CIV-01 · Bygg & Grund Entreprenad AB 1.3% of €18.400m
MEC-02 · OEM Stahltechnik GmbH 0.0% of €32.000m
INF-03 · Mark & Anläggning AB 0.7% of €7.200m
Outcomes · approved vs rejected, by category
| Approved | Value | Rejected | Rate | |
|---|---|---|---|---|
| Schedule measure | 2 | €220.4k | 0 | 100% |
| Regulatory / statutory / permit requirement | 1 | €47.9k | 0 | 100% |
| Quality / rework | 1 | €23.8k | 0 | 100% |
| Scope addition (owner-initiated) | 0 | €0 | 1 | 0% |
Values reconcile to approved cost to date (€292.1k).
Decision quality
- Decided to date
- 5 · 4 approved, 1 rejected
- Approval rate
- 80%
- Cycle, approved
- —
- Cycle, rejected
- —
- Withdrawn / superseded
- 0 / 1
Slow rejections are their own signal: a change that takes weeks to kill consumed weeks of everyone's attention.
Every figure is computed live from the register · pending exposure excludes drafts and credits are reported unnetted · 491,412 pending across 5 changes.