NSV-CR-0021In Assessment
Temporary drainage to canteen compound
Description
Persistent surface water at the canteen compound after the spring melt; temporary drainage run to the east culvert.
Assessments · Rev A (parallel)
- No assessments recorded yet.
Attachments
None yet.
Facts
- Area
- Infrastructure
- Discipline
- Civil / Geotechnical
- Contract
- INF-03 · Mark & Anläggning AB
- Category
- Design development / engineering change
- Reason
- Weather / force majeure event
- Milestone
- —
- Schedule
- —
- Raised by
- Maria Holm · 27 May
- Current actor
- Sofia Ahlgren · day 13
Estimate
€14,912
ROM · entered SEK 170,000 @ 11.4 · approved value: pending