NSV-CR-0017Rev BIn Approval
Revised piling methodology: unforeseen obstructions, MS-North
Description
TriggerPiling in Area MS-North encountered buried obstructions and artesian groundwater behaviour inconsistent with the geotechnical baseline GEO-RPT-004 (boreholes BH-112 to BH-118). Productivity fell from 6 to 1.5 piles per shift. Contractor early warning EW-CIV-014 received 11 May 2026.
Contractual basisAB 04 ch. 4 unforeseen conditions; owner risk per contract CIV-01, appendix 3 (risk allocation).
Scope of changeRevised piling methodology (pre-augering and temporary casing) for the remaining 64 piles in MS-North; standby and partial demobilisation costs for 12 to 16 May.
Do-nothing consequencePiling continues at current productivity: forecast +41 days to milestone M3, exposure to a prolongation claim under CIV-01, and obstruction damage risk to the piling rig.
AskApprove the revised methodology and release EUR 348,500 from contingency.
Assessments · Rev B (parallel)
- DoneLena Vikström · technical · 2 Jun
Methodology sound; pre-augering mitigates obstruction risk. Recommend proceed. - DoneSofia Ahlgren · cost & schedule · 3 Jun
EUR 348,500 Budget ±30%, build-up attached. +18 calendar days to M3, critical path confirmed against P6 update. - DoneSofia Ahlgren · contractual · 3 Jun
Entitlement confirmed: genuine owner-risk item, not contractor performance. - DonePär Eklund · hse · 5 Jun · requested by Anna Lindqvist, non-blocking
No additional HSE controls beyond the revised method statement. No objection.
Attachments
GEO-RPT-004 extract.pdf · EW-CIV-014.pdf · Method statement rev 2.pdf · Cost build-up.xlsx
Facts
- Area
- Meltshop
- Discipline
- Civil / Geotechnical
- Contract
- CIV-01 · Bygg & Grund Entreprenad AB
- Category
- Unforeseen site conditions
- Reason
- Unforeseen ground or site conditions
- Milestone
- M3 · Foundations complete
- Schedule
- +18 days · critical path
- Raised by
- Maria Holm · 12 May
- Current actor
- Steering Committee · day 1
Estimate
Budget · approved value: pending
History (append-only)- 26 MaySofia Ahlgren 348,500 · Budget · basis of estimate attached
- 19 MaySofia Ahlgren 365,000 · ROM
- 12 MayMaria Holm 290,000 · ROM · first estimate
| 3.2.1 | Pre-augering, 64 piles | 212,000 |
| 3.2.2 | Temporary casing | 58,500 |
| 3.9.1 | Standby, 12 to 16 May | 64,000 |
| 3.9.2 | Partial demobilisation | 14,000 |
| reconciles to header | 348,500 |
Contingency release
€348,500 flagged for release. Sign-off by Project Director, non-delegable, signed 12 Jun. The change is not Approved until both the route and this signature are complete.