NSV · Norra Stålverket expansion · base EUR · SEK, USD enabled · contingency €2,500,000Raise a change
Change request

NSV-CR-0017Rev BIn Approval

Revised piling methodology: unforeseen obstructions, MS-North

Description

TriggerPiling in Area MS-North encountered buried obstructions and artesian groundwater behaviour inconsistent with the geotechnical baseline GEO-RPT-004 (boreholes BH-112 to BH-118). Productivity fell from 6 to 1.5 piles per shift. Contractor early warning EW-CIV-014 received 11 May 2026.

Contractual basisAB 04 ch. 4 unforeseen conditions; owner risk per contract CIV-01, appendix 3 (risk allocation).

Scope of changeRevised piling methodology (pre-augering and temporary casing) for the remaining 64 piles in MS-North; standby and partial demobilisation costs for 12 to 16 May.

Do-nothing consequencePiling continues at current productivity: forecast +41 days to milestone M3, exposure to a prolongation claim under CIV-01, and obstruction damage risk to the piling rig.

AskApprove the revised methodology and release EUR 348,500 from contingency.

Assessments · Rev B (parallel)

  • Done
    Lena Vikström · technical · 2 Jun
    Methodology sound; pre-augering mitigates obstruction risk. Recommend proceed.
  • Done
    Sofia Ahlgren · cost & schedule · 3 Jun
    EUR 348,500 Budget ±30%, build-up attached. +18 calendar days to M3, critical path confirmed against P6 update.
  • Done
    Sofia Ahlgren · contractual · 3 Jun
    Entitlement confirmed: genuine owner-risk item, not contractor performance.
  • Done
    Pär Eklund · hse · 5 Jun · requested by Anna Lindqvist, non-blocking
    No additional HSE controls beyond the revised method statement. No objection.

Attachments

GEO-RPT-004 extract.pdf · EW-CIV-014.pdf · Method statement rev 2.pdf · Cost build-up.xlsx

Facts

Area
Meltshop
Discipline
Civil / Geotechnical
Contract
CIV-01 · Bygg & Grund Entreprenad AB
Category
Unforeseen site conditions
Reason
Unforeseen ground or site conditions
Milestone
M3 · Foundations complete
Schedule
+18 days · critical path
Raised by
Maria Holm · 12 May
Current actor
Steering Committee · day 1

Estimate

348,500

Budget · approved value: pending

History (append-only)
  • 26 May
    Sofia Ahlgren 348,500 · Budget · basis of estimate attached
  • 19 May
    Sofia Ahlgren 365,000 · ROM
  • 12 May
    Maria Holm 290,000 · ROM · first estimate
CBS breakdown · maintained by the Change Manager
3.2.1Pre-augering, 64 piles212,000
3.2.2Temporary casing58,500
3.9.1Standby, 12 to 16 May64,000
3.9.2Partial demobilisation14,000
reconciles to header348,500

Contingency release

348,500 flagged for release. Sign-off by Project Director, non-delegable, signed 12 Jun. The change is not Approved until both the route and this signature are complete.